Construction Update

For the week of September 5th work on the construction site will include continued spraying of the steel with fireproofing material. Starting Tuesday framing will begin for the exterior walls. Also on Tuesday the steel will be put up for the core area, multipurpose room and offices. On Friday the trusses are due to be delivered for the roof.