Construction Update - 10/15/10


Roofing of the East wing began this week and setting of trusses will be completed on Wednesday. Application of ice and water shield will also be done on Wednesday. Thursday the pouring of slabs in the last section of East wing will take place.

Exterior wall framing will begin in the West wing on Saturday. Interior framing has begun in the core of the building. The last of the structural steel will be put in place next week.

Base pavement was put in yesterday. Will begin running the heat lines for the bio-mass from the new construction to the current facility and will be brought in through the maintenance shop on Friday.