Construction Update - 11/24/10

44 windows have been installed on the first floor of the East Wing, and it is planned to install another 44 next week on the second floor. The heat was turned on in the East Wing on 11/19. It is planned to have heat on in the West Wing next week and the Core the following week. There are 71 workers on the job site. Insulation is being put on the roof and when complete will be 7 1/2 inches thick.